Stuttgart Vaihingen Logistics Hub

Stuttgart Vaihingen Logistics Hub

Client Vaihinger Logistik GmbH · Industriestraße 18, 70563 StuttgartCompletedTargeting DGNB Silver
ContractorGoldbeck GmbH
Schedule2025-06-01 ~ 2025-12-15
Building typeIndustrial
Total carbon
784,578kgCO₂eq
As of snapshot 2025-12-15
Site deliveries
22entries
From the moment of QR scan
Materials / suppliers
7types · 7 suppliers
Categorised by delivered material
Top carbon driver
56.4% of this project's carbon comes from Concrete
Low-carbon alternativesvs current 240.5 kgCO₂eq/
EcoCrete® CEM III/B C30/37
EcoCrete® CEM III/B C30/37
Heidelberg Materials · IBU EPD
156.3kgCO₂eq/
151,560 · 35%
ECOPact® CEM II/A-LL C30/37
ECOPact® CEM II/A-LL C30/37
Holcim · IBU EPD
204.4kgCO₂eq/
64,980 · 15%
Quick transport scenarios
for Ready-mix Concrete C30/37 (XC2) · current transport 9,374 kgCO₂eq
Click a chip — savings apply to the delivery row below.

Carbon share by material

Production stage
784,578
kgCO₂eq
  • Concrete56.4%
  • Structural28.2%
  • Reinforcing9.4%
  • Insulation2.7%
  • Bituminous2.7%
  • Windows0.3%
  • Plasterboard0.3%

Cumulative carbon over time

Unit: kgCO₂eq

Cumulative carbon adds up with every delivery. Large material shipments cause visible jumps.

0384,000768,00006-1506-2207-0207-0507-0807-1207-1807-2208-0408-1208-2008-2709-0509-1509-2210-0510-1210-1810-2511-0511-1211-22

Material lifecycle

At-a-glance view of how far the materials in this project have travelled.

STEP 1
Production
EPD-listed material leaves the plant
STEP 2
Transport
Dispatched on the delivery route
STEP 3
Site arrival
QR registered on site
STEP 4
Verification
Verification hash matched
STEP 5
Certification
Submission package ready

Site delivery records

Materials sorted by carbon contribution. Click a row to see step-by-step traceability and a transport simulation.

Material
Progress
Quantity
Carbon
Share of total
Ready-mix Concrete C30/37 (XC2)
Ready-mix Concrete C30/37 (XC2)
Concrete · BetonWerk
1,800
442,274kgCO₂eq
56.4%
Structural Steel S355J2 (Hot-rolled Section)
Structural Steel S355J2 (Hot-rolled Section)
Structural Steel · Stahlbau
200 t
220,712kgCO₂eq
28.1%
Reinforcing Steel Rebar B500B Ø12mm
Reinforcing Steel Rebar B500B Ø12mm
Structural Steel · Stahlbau
95 t
74,438kgCO₂eq
9.5%
XPS Insulation Board 50mm
XPS Insulation Board 50mm
Insulation · Insulux
6,500
21,246kgCO₂eq
2.7%
Bituminous Roofing Membrane SBS 4mm
Bituminous Roofing Membrane SBS 4mm
Roofing · Dachschutz
4,200
21,030kgCO₂eq
2.7%
Gypsum Plasterboard 12.5mm
Gypsum Plasterboard 12.5mm
Interior Finish · PlasterPro
1,200
2,490kgCO₂eq
0.3%
Triple-glazed Window (Uw 0.8)
Triple-glazed Window (Uw 0.8)
Windows & Doors · FensterWerk
45 set
2,388kgCO₂eq
0.3%
Ledger verification
Delivery records
All records tamper-evident
22 / 22 done
Carbon snapshot
2025-12-15 15:00 · Up to latest delivery
Snapshot locked