All material records
Delivery and snapshot entries across every active project. See when each record was sealed and how it can be verified.
Berlin Mitte Office New Build40 entries
Delivery — Reinforcing Steel Rebar B500B Ø12mm
45 t · Foundation cages east · Rebar batch 1 — foundation east strip cages
Record hash665ac3aa69…96a80ba9db
Delivery recorded03-12 08:01
Internally verified03-12 07:02
Snapshot locked
Delivery — Reinforcing Steel Rebar B500B Ø12mm
45 t · Foundation cages west · Rebar batch 2 — foundation west strip cages
Record hash8c5d3e13a8…b7c9546ace
Delivery recorded03-17 08:01
Internally verified03-17 07:02
Snapshot locked
Delivery — Lime-Cement Mortar M5 (Dry-mix)
22 t · Material yard · Mortar batch 1/5 — bulk silo fill for masonry phase
Record hashb25fb87ce6…d8ea9d2bc1
Delivery recorded03-19 10:01
Internally verified03-19 09:02
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
360 m³ · Foundation east bay A · Pour event 1/7 — east-bay A (50 mixers, 4h)
Record hashd86232e525…f90be5ecb4
Delivery recorded03-22 07:31
Internally verified03-22 06:32
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
400 m³ · Foundation east bay B · Pour event 2/7 — east-bay B (55 mixers, 5h)
Record hashfe64ad4e64…1a2d2eada7
Delivery recorded03-25 07:31
Internally verified03-25 06:32
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
440 m³ · Foundation west bay · Pour event 3/7 — west-bay (switched plant for capacity)
Record hash246727b7a3…3b4e776e9a
Delivery recorded03-28 07:31
Internally verified03-28 05:32
Snapshot locked
Delivery — Structural Steel S355J2 (Hot-rolled Section)
38 t · Site lay-down area · Steel batch 1/5 — core columns L1-L3
Record hash4a69a220e2…5c6fc02f8d
Delivery recorded03-31 08:01
Internally verified03-31 06:02
Snapshot locked
Delivery — Reinforcing Steel Rebar B500B Ø12mm
42 t · Core walls + L1 cages · Rebar batch 3 — core shear walls + L1 slab
Record hash104475f932…6d7c7ce150
Delivery recorded04-02 08:01
Internally verified04-02 06:02
Snapshot locked
Delivery — Structural Steel S355J2 (Hot-rolled Section)
42 t · Site lay-down area · Steel batch 2/5 — beams L1-L4
Record hash3646f06271…8e9dc5a243
Delivery recorded04-05 08:01
Internally verified04-05 06:02
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
380 m³ · Core walls + L1 slab · Pour event 4/7 — cores + L1 slab
Record hashc02ce3ec10…c85a930291
Delivery recorded04-07 07:31
Internally verified04-07 05:32
Snapshot locked
Delivery — XPS Insulation Board 50mm
1500 m² · East façade staging · XPS insulation batch 1 — east façade
Record hash9a2a6983d1…a7394a419e
Delivery recorded04-09 09:31
Internally verified04-09 07:32
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
340 m³ · L2 slab + L4 cores · Pour event 5/7 — L2 slab + L4 cores
Record hash7427ef1a93…86180180ab
Delivery recorded04-11 07:31
Internally verified04-11 05:32
Snapshot locked
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · Site lay-down area · Steel batch 3/5 — beams L5-L7
Record hash4e2574b154…65f6b8bfb8
Delivery recorded04-13 08:01
Internally verified04-13 06:02
Snapshot locked
Delivery — Reinforcing Steel Rebar B500B Ø12mm
48 t · L3-L5 slab cages · Rebar batch 4 — L3-L5 slab cages
Record hash5836cd900c…4cdfb6065d
Delivery recorded04-14 08:01
Internally verified04-14 06:02
Snapshot locked
Project carbon snapshot
Carbon snapshot across all project deliveries
Record hashe8ca56acc0…88dbef84d1
Snapshot recorded04-15 16:30
Internally verified04-15 14:31
Snapshot locked
Delivery — XPS Insulation Board 50mm
1500 m² · West façade staging · XPS insulation batch 2 — west façade
Record hash32345327cd…2bbe6d456a
Delivery recorded04-17 09:31
Internally verified04-17 07:32
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
300 m³ · L3 slab · Pour event 6/7 — L3 slab
Record hash0c31d8be8e…0a9d248477
Delivery recorded04-19 07:31
Internally verified04-19 05:32
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · Site lay-down area · Steel batch 4/5 — columns L8-L10
Record hashe62f5e554f…e97bdbc384
Delivery recorded04-21 08:01
Internally verified04-21 06:02
Verified
Delivery — Gypsum Plasterboard 12.5mm
3000 m² · L1 interiors · Plasterboard batch 1 — L1 partitions
Record hash901910a419…c0504cfaf9
Delivery recorded04-23 13:31
Internally verified04-23 11:32
Verified
Delivery — Triple-glazed Window (Uw 0.8)
80 set · L1-L2 façade · Windows batch 1/5 — L1-L2 curtain-wall units
Record hash6a16963bda…9f2f043a06
Delivery recorded04-25 11:01
Internally verified04-25 09:02
Verified
Delivery — Clay Hollow Brick HLz 1.2/12 (240mm)
600 m² · East façade workshop · Brick batch 1 — east façade infill (22 pallets)
Record hash3ec44a1784…9b8a02a2ba
Delivery recorded04-27 09:01
Internally verified04-27 07:02
Verified
Delivery — XPS Insulation Board 50mm
1500 m² · North/South façade · XPS insulation batch 3 — north + south façade
Record hash64c6c480c3…bcab4b63ad
Delivery recorded04-29 09:31
Internally verified04-29 07:32
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
280 m³ · L4-L5 cores · Pour event 7/7 — upper cores topping out
Record hashf2bf554506…59477120d4
Delivery recorded05-01 07:31
Internally verified05-01 05:32
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · Site lay-down area · Steel batch 5/5 — secondary frame + bracing
Record hash18c1cfae45…7a68b9e1c7
Delivery recorded05-03 08:01
Internally verified05-03 06:02
Verified
Delivery — Lime-Cement Mortar M5 (Dry-mix)
22 t · Material yard · Mortar batch 2/5 — east-façade brick laying
Record hasha6ba607388…1704df9eee
Delivery recorded05-05 10:01
Internally verified05-05 08:02
Verified
Delivery — Gypsum Plasterboard 12.5mm
3000 m² · L2 interiors · Plasterboard batch 2 — L2 partitions
Record hashccbcdadcc7…3826285fe1
Delivery recorded05-07 13:31
Internally verified05-07 11:32
Verified
Delivery — Reinforcing Steel Rebar B500B Ø12mm
40 t · Upper slab cages · Rebar batch 5 — L6-L10 slab cages
Record hash5ab56ba10a…d5c24e1d08
Delivery recorded05-09 08:01
Internally verified05-09 06:02
Verified
Delivery — Lime-Cement Mortar M5 (Dry-mix)
22 t · Material yard · Mortar batch 3/5 — west-façade brick laying
Record hashe11b419894…14580eaa35
Delivery recorded05-09 10:01
Internally verified05-09 08:02
Verified
Delivery — Clay Hollow Brick HLz 1.2/12 (240mm)
600 m² · West façade workshop · Brick batch 2 — west façade infill (22 pallets)
Record hash80b7e60a49…f6e396ddfb
Delivery recorded05-11 09:01
Internally verified05-11 07:02
Verified
Delivery — Triple-glazed Window (Uw 0.8)
80 set · L3-L4 façade · Windows batch 2/5 — L3-L4 curtain wall
Record hash0eb076cf8d…937fbc9b22
Delivery recorded05-13 11:01
Internally verified05-13 09:02
Verified
Delivery — Gypsum Plasterboard 12.5mm
3000 m² · L3 interiors · Plasterboard batch 3 — L3 partitions
Record hash34b2f138cb…b4a1055c15
Delivery recorded05-15 13:31
Internally verified05-15 11:32
Verified
Delivery — Lime-Cement Mortar M5 (Dry-mix)
22 t · Material yard · Mortar batch 4/5 — north-façade brick laying
Record hashbb18c72f55…f336c5e942
Delivery recorded05-16 10:01
Internally verified05-16 08:02
Verified
Delivery — Clay Hollow Brick HLz 1.2/12 (240mm)
600 m² · North façade workshop · Brick batch 3 — north façade infill (22 pallets)
Record hashfd0c63221a…4e905a2483
Delivery recorded05-17 09:01
Internally verified05-17 07:02
Verified
Delivery — Triple-glazed Window (Uw 0.8)
80 set · L5-L6 façade · Windows batch 3/5 — L5-L6 curtain wall
Record hashd709e8b9db…2d6f116390
Delivery recorded05-19 11:01
Internally verified05-19 09:02
Verified
Delivery — Gypsum Plasterboard 12.5mm
3000 m² · L4-L5 interiors · Plasterboard batch 4 — L4-L5 partitions
Record hash491157f498…90d2eba669
Delivery recorded05-21 13:31
Internally verified05-21 11:32
Verified
Delivery — Lime-Cement Mortar M5 (Dry-mix)
22 t · Material yard · Mortar batch 5/5 — internal plastering & screed
Record hash2d20366a11…569aa02c1b
Delivery recorded05-23 10:01
Internally verified05-23 08:02
Verified
Delivery — Triple-glazed Window (Uw 0.8)
80 set · L7-L8 façade · Windows batch 4/5 — L7-L8 curtain wall
Record hash230edd8b59…6fb1a2e576
Delivery recorded05-23 11:01
Internally verified05-23 09:02
Verified
Delivery — Bituminous Roofing Membrane SBS 4mm
1200 m² · Rooftop level · SBS roofing membrane — full rooftop coverage
Record hash95164cc616…d2157d284f
Delivery recorded05-26 08:31
Internally verified05-26 06:32
Verified
Delivery — Engineered Oak Flooring 22mm (3-ply)
600 m² · Lobby + executive floor · Engineered oak flooring — lobby & exec floors
Record hash6f13d25dd7…b1f434675c
Delivery recorded05-28 13:01
Internally verified05-28 11:02
Verified
Delivery — Triple-glazed Window (Uw 0.8)
80 set · L9-L10 + parapet · Windows batch 5/5 — L9-L10 + parapet glazing
Record hash071dbc01d3…3579576b28
Delivery recorded05-30 11:01
Internally verified05-30 09:02
Verified
Hamburg Mönckeberg School Refurbishment14 entries
Delivery — Lime-Cement Mortar M5 (Dry-mix)
9 t · Site yard · Mortar batch 1 — initial repointing
Record hashf267b22057…5cc399df8d
Delivery recorded10-08 10:31
Internally verified10-08 08:32
Snapshot locked
Delivery — XPS Insulation Board 50mm
1500 m² · North façade · XPS finish-layer insulation — north façade
Record hash806042e59a…f95fbf9cb4
Delivery recorded10-12 09:31
Internally verified10-12 07:32
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
55 m³ · Foundation east · Pour event 1/2 — east foundation strengthening
Record hasha662bd4ed9…1a81085da7
Delivery recorded10-22 08:01
Internally verified10-22 06:02
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
45 m³ · Foundation west · Pour event 2/2 — west foundation strengthening
Record hash345b4e131c…b71d2e1ace
Delivery recorded10-25 08:01
Internally verified10-25 06:02
Snapshot locked
Delivery — Lime-Cement Mortar M5 (Dry-mix)
9 t · Site yard · Mortar batch 2 — finish repointing + screed
Record hash5a5dc87c5b…d83e76dbc1
Delivery recorded11-08 10:31
Internally verified11-08 09:32
Snapshot locked
Delivery — Clay Hollow Brick HLz 1.2/12 (240mm)
320 m² · Façade workshop · Brick batch — façade spot repair (12 pallets)
Record hashe85659419f…75da9c98e8
Delivery recorded11-15 09:16
Internally verified11-15 08:17
Snapshot locked
Delivery — Bituminous Roofing Membrane SBS 4mm
400 m² · South wing roof · SBS membrane batch 1 — south wing
Record hash0e58d3aade…96fbe559db
Delivery recorded12-05 08:46
Internally verified12-05 07:47
Snapshot locked
Delivery — Bituminous Roofing Membrane SBS 4mm
350 m² · North wing roof · SBS membrane batch 2 — north wing
Record hash9c51646f21…33980b1702
Delivery recorded12-15 08:46
Internally verified12-15 07:47
Snapshot locked
Delivery — Gypsum Plasterboard 12.5mm
1500 m² · Ground-floor classrooms · Plasterboard batch 1 — ground-floor partitions
Record hashc253ded860…54b953d7f5
Delivery recorded01-12 13:21
Internally verified01-12 12:22
Snapshot locked
Delivery — Gypsum Plasterboard 12.5mm
1500 m² · Upper-floor classrooms · Plasterboard batch 2 — upper-floor partitions
Record hash8bea854222…6e4d0919e3
Delivery recorded01-20 13:21
Internally verified01-20 12:22
Snapshot locked
Delivery — Triple-glazed Window (Uw 0.8)
40 set · South wing windows · Triple-glazed units batch 1 — south wing
Record hash65e80ad9e3…4d2bc058f0
Delivery recorded02-08 10:46
Internally verified02-08 09:47
Snapshot locked
Delivery — Triple-glazed Window (Uw 0.8)
40 set · North wing windows · Triple-glazed units batch 2 — north wing
Record hashd7ef7a14a0…b08f9a9bc9
Delivery recorded02-12 10:46
Internally verified02-12 09:47
Snapshot locked
Delivery — Engineered Oak Flooring 22mm (3-ply)
1200 m² · All classroom interiors · Engineered oak flooring — full renewal
Record hashb1ecffab61…8f6e51dad6
Delivery recorded02-20 11:01
Internally verified02-20 10:02
Snapshot locked
Project carbon snapshot
Carbon snapshot across all project deliveries
Record hash76c2e77104…25781541f8
Snapshot recorded03-15 15:00
Internally verified03-15 14:01
Snapshot locked
Frankfurt Messeturm Hotel Tower40 entries
Delivery — Reinforcing Steel Rebar B500B Ø12mm
40 t · Foundation cages · Rebar batch 1 — foundation cages
Record hashb9204b8e9a…5a3b41d667
Delivery recorded01-22 08:01
Internally verified01-22 07:02
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
35 t · Site lay-down area · Steel batch 1 — temporary works + tower-crane base
Record hashdf22c5f7d8…7b5c8a975a
Delivery recorded01-26 08:01
Internally verified01-26 07:02
Verified
Delivery — Reinforcing Steel Rebar B500B Ø12mm
38 t · Core wall cages · Rebar batch 2 — core shear-wall cages
Record hash0525406017…9c7dd3584d
Delivery recorded01-30 08:01
Internally verified01-30 07:02
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
380 m³ · Foundation east · Pour event 1/6 — east foundation raft
Record hashfb13e7815f…b594d611a8
Delivery recorded02-02 07:46
Internally verified02-02 06:47
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
360 m³ · Foundation west · Pour event 2/6 — west foundation raft
Record hash211661ea9e…d6b61ed29b
Delivery recorded02-04 07:46
Internally verified02-04 06:47
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
32 t · Podium frame · Steel batch 2 — podium frame
Record hash4718dc53dd…f7d767938e
Delivery recorded02-08 08:01
Internally verified02-08 07:02
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
320 m³ · Core walls + L1 · Pour event 3/6 — core walls + L1 slab
Record hash6d1b56bc1c…18f8b05481
Delivery recorded02-12 07:46
Internally verified02-12 06:47
Verified
Delivery — Reinforcing Steel Rebar B500B Ø12mm
35 t · Tower slab cages · Rebar batch 3 — tower slab cages L2-L6
Record hash6309fddd63…310fb30ddc
Delivery recorded02-15 08:01
Internally verified02-15 07:02
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · Tower columns L2-L6 · Steel batch 3 — tower columns lower zone
Record hash890c7846a2…5230fbcecf
Delivery recorded02-18 08:01
Internally verified02-18 07:02
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · Site lay-down area · Steel batch 7 — podium secondary frame
Record hashddca7bcb8e…afbfb60e36
Delivery recorded02-22 08:01
Internally verified02-22 07:02
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
380 m³ · Tower slabs L2-L4 · Pour event 4/6 — tower slabs L2-L4 (switched plant for capacity)
Record hash12f26bd041…8cedc92f1d
Delivery recorded02-25 07:46
Internally verified02-25 06:47
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
35 t · Tower columns L7-L10 · Steel batch 4 — tower columns mid zone
Record hasheceff16702…6bcc806e2a
Delivery recorded03-02 08:01
Internally verified03-02 07:02
Verified
Delivery — Reinforcing Steel Rebar B500B Ø12mm
40 t · Tower slab cages L7-L11 · Rebar batch 4 — tower slab cages mid zone
Record hashc6ed76fec4…4aab37ad37
Delivery recorded03-08 08:01
Internally verified03-08 07:02
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · Site lay-down area · Steel batch 8 — tower secondary beams + bracing
Record hash7fe5be4e42…1a2dd658a7
Delivery recorded03-10 08:01
Internally verified03-10 07:02
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
320 m³ · Tower slabs L5-L7 · Pour event 5/6 — tower slabs L5-L7
Record hasha0eafc9585…2989eeec44
Delivery recorded03-12 07:46
Internally verified03-12 06:47
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
38 t · Tower columns L11-L14 · Steel batch 5 — tower columns upper zone
Record hash7ae8822c46…0868a62b51
Delivery recorded03-15 08:01
Internally verified03-15 07:02
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
360 m³ · Tower slabs L8-L10 · Pour event 7/9 — tower slabs L8-L10
Record hashb7c8016250…8e9e6d4d43
Delivery recorded03-19 07:46
Internally verified03-19 06:47
Verified
Delivery — XPS Insulation Board 50mm
1300 m² · Lower-zone façade · XPS insulation batch 1 — lower zone
Record hash54e607c307…e7475d6a5e
Delivery recorded03-20 09:16
Internally verified03-20 08:17
Verified
Delivery — Clay Hollow Brick HLz 1.2/12 (240mm)
600 m² · Podium façade east · Brick batch 1 — podium façade east (22 pallets)
Record hash2ee38d5ac8…c62614a96b
Delivery recorded03-25 09:31
Internally verified03-25 08:32
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
340 m³ · Tower slabs L11-L12 · Pour event 8/9 — tower slabs L11-L12
Record hash91c586f911…6d7d248c50
Delivery recorded03-26 07:46
Internally verified03-26 06:47
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
300 m³ · Tower slabs L13-L14 + setbacks · Pour event 9/9 — top floors + setback walls
Record hash03ccf634cd…d0e0fecf29
Delivery recorded04-01 07:46
Internally verified04-01 05:47
Verified
Delivery — Reinforcing Steel Rebar B500B Ø12mm
27 t · Roof slab cages · Rebar batch 5 — roof slab + rooftop plant
Record hash08e112f189…a504cbe878
Delivery recorded04-02 08:01
Internally verified04-02 06:02
Verified
Delivery — Triple-glazed Window (Uw 0.8)
80 set · L1-L4 façade · Triple-glazed units batch 1 — L1-L4 (80 sets)
Record hashe2de98884a…84e3832785
Delivery recorded04-05 10:31
Internally verified04-05 08:32
Verified
Delivery — Ready-mix Concrete C30/37 (XC2)
240 m³ · Tower roof + rooftop plant · Pour event 6/6 — roof slab + rooftop plant deck
Record hashbcdc1e1f0b…63c23a6692
Delivery recorded04-08 07:46
Internally verified04-08 05:47
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · Rooftop plant · Steel batch 6 — rooftop plant frames + parapets
Record hashd13a84dbd8…3ff420b0e6
Delivery recorded04-12 08:01
Internally verified04-12 06:02
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · Site lay-down area · Steel batch 9 — façade brackets + curtain-wall mullions
Record hash59e343e503…f90c8d97b4
Delivery recorded04-15 08:01
Internally verified04-15 06:02
Verified
Delivery — XPS Insulation Board 50mm
1300 m² · Middle-zone façade · XPS insulation batch 2 — middle zone
Record hashf73cff4417…60156971d9
Delivery recorded04-18 09:16
Internally verified04-18 07:17
Verified
Delivery — Triple-glazed Window (Uw 0.8)
80 set · L5-L8 façade · Triple-glazed units batch 2 — L5-L8 (80 sets)
Record hash853590095a…fdb18f2f00
Delivery recorded04-25 10:31
Internally verified04-25 08:32
Verified
Delivery — Gypsum Plasterboard 12.5mm
4000 m² · L1-L4 guest rooms · Plasterboard batch 1 — L1-L4 guest-room partitions
Record hashab380a7299…1ed2d7eff3
Delivery recorded05-02 13:31
Internally verified05-02 11:32
Verified
Delivery — Clay Hollow Brick HLz 1.2/12 (240mm)
600 m² · Podium façade west · Brick batch 2 — podium façade west (22 pallets)
Record hash69446e7fd3…c37943b4b2
Delivery recorded05-05 09:31
Internally verified05-05 07:32
Verified
Delivery — XPS Insulation Board 50mm
1200 m² · Upper-zone façade · XPS insulation batch 3 — upper zone
Record hash8f46e8e812…e49a8c75a5
Delivery recorded05-08 09:16
Internally verified05-08 07:17
Verified
Delivery — Bituminous Roofing Membrane SBS 4mm
900 m² · Podium terrace · SBS membrane batch 1 — podium terrace
Record hash1d3f79ad56…8136b232cc
Delivery recorded05-10 08:01
Internally verified05-10 06:02
Verified
Delivery — Triple-glazed Window (Uw 0.8)
80 set · L9-L11 façade · Triple-glazed units batch 3 — L9-L11 (80 sets)
Record hash4341f41695…a257faf3bf
Delivery recorded05-12 10:31
Internally verified05-12 08:32
Verified
Delivery — Gypsum Plasterboard 12.5mm
4000 m² · L5-L8 guest rooms · Plasterboard batch 2 — L5-L8 guest-room partitions
Record hash014e5823cf…47fe66b87e
Delivery recorded05-13 13:31
Internally verified05-13 11:32
Verified
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · Rooftop level · Steel batch 10 — rooftop plant frames + parapet
Record hash978303f91a…6db7da1b50
Delivery recorded05-15 08:01
Internally verified05-15 06:02
Verified
Delivery — Engineered Oak Flooring 22mm (3-ply)
850 m² · Suite + lobby staging · Engineered oak flooring — suites & lobby
Record hash2750d28c0e…681faf7971
Delivery recorded05-15 13:01
Internally verified05-15 11:02
Verified
Delivery — Gypsum Plasterboard 12.5mm
4000 m² · L9-L11 guest rooms · Plasterboard batch 3 — L9-L11 guest-room partitions
Record hash4fd1eb064b…122390510f
Delivery recorded05-18 13:31
Internally verified05-18 11:32
Verified
Delivery — Bituminous Roofing Membrane SBS 4mm
900 m² · Tower rooftop · SBS membrane batch 2 — tower rooftop
Record hash29cf709d0c…f10247901c
Delivery recorded05-20 08:01
Internally verified05-20 06:02
Verified
Delivery — Triple-glazed Window (Uw 0.8)
80 set · L12-L14 façade · Triple-glazed units batch 4 — L12-L14 (80 sets)
Record hash9bd6dfd8c9…546621d2f5
Delivery recorded05-22 10:31
Internally verified05-22 08:32
Verified
Delivery — Gypsum Plasterboard 12.5mm
4000 m² · L12-L14 + corridors · Plasterboard batch 4 — L12-L14 + corridors
Record hash75d4656f8a…3344d91202
Delivery recorded05-25 13:31
Internally verified05-25 11:32
Verified
Stuttgart Vaihingen Logistics Hub23 entries
Delivery — Reinforcing Steel Rebar B500B Ø12mm
35 t · Slab cages east · Rebar batch 1 — east slab cages
Record hashc77544ad48…81d5643bcc
Delivery recorded06-15 08:01
Internally verified06-15 06:02
Snapshot locked
Delivery — Reinforcing Steel Rebar B500B Ø12mm
35 t · Slab cages west · Rebar batch 2 — west slab cages
Record hash397cb3e805…e4393e7ea5
Delivery recorded06-22 08:01
Internally verified06-22 06:02
Snapshot locked
Delivery — Reinforcing Steel Rebar B500B Ø12mm
25 t · Dock-leveler pads · Rebar batch 3 — dock-leveler pads + plinth cages
Record hash137a397fc6…c317f5bdb2
Delivery recorded07-02 08:01
Internally verified07-02 06:02
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
380 m³ · West slab bay A · Pour event 1/5 — west slab bay A
Record hash556dd5728c…1e7189f8f3
Delivery recorded07-05 07:46
Internally verified07-05 05:47
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
400 m³ · West slab bay B · Pour event 2/5 — west slab bay B
Record hash2f6b5b094d…fd50413800
Delivery recorded07-08 07:46
Internally verified07-08 05:47
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
450 m³ · East slab bay · Pour event 3/5 — east slab bay (largest pour)
Record hasha172ca4409…60b41b7ad9
Delivery recorded07-12 07:46
Internally verified07-12 05:47
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
380 m³ · Dock pads + plinth · Pour event 4/5 — dock-leveler pads + column footings
Record hash7b704fdbcb…3f92d2b9e6
Delivery recorded07-18 07:46
Internally verified07-18 05:47
Snapshot locked
Delivery — Ready-mix Concrete C30/37 (XC2)
190 m³ · Office wing slab · Pour event 5/5 — office wing slab
Record hash1d8b925e7e…aa00f30457
Delivery recorded07-22 07:46
Internally verified07-22 05:47
Snapshot locked
Delivery — Structural Steel S355J2 (Hot-rolled Section)
50 t · East portal frame · Steel batch 1 — east portal frame columns + rafters
Record hashf78917f540…89dfaa4364
Delivery recorded08-04 07:31
Internally verified08-04 05:32
Snapshot locked
Delivery — Structural Steel S355J2 (Hot-rolled Section)
45 t · East portal frame · Steel batch 2 — east portal frame bracing + purlins
Record hash6ee058eb14…cfc73d5c96
Delivery recorded08-12 07:31
Internally verified08-12 05:32
Snapshot locked
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · West portal frame · Steel batch 3 — west portal frame columns + rafters
Record hash94e2d35453…f0e8861d89
Delivery recorded08-20 07:31
Internally verified08-20 05:32
Snapshot locked
Delivery — Structural Steel S355J2 (Hot-rolled Section)
40 t · West portal frame · Steel batch 4 — west portal frame bracing + purlins
Record hash22db641996…8d84abdab0
Delivery recorded08-27 07:31
Internally verified08-27 05:32
Snapshot locked
Delivery — Structural Steel S355J2 (Hot-rolled Section)
25 t · Office wing + secondary · Steel batch 5 — office wing + secondary steel
Record hash48ddde82d5…aea5f49ba3
Delivery recorded09-05 07:31
Internally verified09-05 05:32
Snapshot locked
Delivery — XPS Insulation Board 50mm
1700 m² · East panel staging · XPS sandwich-panel core batch 1 — east half
Record hash06ea428f0f…534c606062
Delivery recorded09-15 09:31
Internally verified09-15 07:32
Snapshot locked
Delivery — XPS Insulation Board 50mm
1700 m² · East panel staging · XPS sandwich-panel core batch 2 — east half
Record hash2cecbcf84e…746da92155
Delivery recorded09-22 09:31
Internally verified09-22 07:32
Snapshot locked
Delivery — XPS Insulation Board 50mm
1700 m² · West panel staging · XPS sandwich-panel core batch 3 — west half
Record hashbae54dbd92…1109cede7c
Delivery recorded10-05 09:31
Internally verified10-05 07:32
Snapshot locked
Delivery — XPS Insulation Board 50mm
1400 m² · Office wing + west panels · XPS batch 4 — office wing + west completion
Record hashe0e7c826d1…322b179f6f
Delivery recorded10-12 09:31
Internally verified10-12 07:32
Snapshot locked
Delivery — Bituminous Roofing Membrane SBS 4mm
1400 m² · Roof east zone · SBS membrane batch 1 — east zone
Record hash9ef42c330b…d7d183642e
Delivery recorded10-18 08:31
Internally verified10-18 06:32
Snapshot locked
Delivery — Bituminous Roofing Membrane SBS 4mm
1400 m² · Roof central zone · SBS membrane batch 2 — central zone
Record hashc4f6a69c4a…f8f2cc2521
Delivery recorded10-25 08:31
Internally verified10-25 06:32
Snapshot locked
Delivery — Bituminous Roofing Membrane SBS 4mm
1400 m² · Roof west zone · SBS membrane batch 3 — west zone
Record hashaf5b0b600a…9c1c85614d
Delivery recorded11-05 08:31
Internally verified11-05 07:32
Snapshot locked
Delivery — Triple-glazed Window (Uw 0.8)
45 set · Office wing façade · Triple-glazed units — office wing (45 sets)
Record hash895890f7cb…7bfb3ca05a
Delivery recorded11-12 10:01
Internally verified11-12 09:02
Snapshot locked
Delivery — Gypsum Plasterboard 12.5mm
1200 m² · Office wing interiors · Plasterboard — office wing partitions
Record hash6356168e8c…5ad9f3df67
Delivery recorded11-22 13:31
Internally verified11-22 12:32
Snapshot locked
Project carbon snapshot
Carbon snapshot across all project deliveries
Record hash9cc561da42…46995e02eb
Snapshot recorded12-15 15:00
Internally verified12-15 14:01
Snapshot locked