buildchain · Project
Frankfurt Messeturm Hotel Tower
In constructionClient: RheinHotels Holding AG

Frankfurt Messeturm Hotel Tower

Friedrich-Ebert-Anlage 49, 60308 Frankfurt am Main
Targeting BREEAM Very Good · DGNB Gold · LEED Silver
Total carbon (production + transport)
1,378,966
kgCO₂eq
Production 1,353,966 · Transport 25,000 · A1-A4
40 deliveries · 9 materials · Last updated 2026-05-15
Site delivery history (by material)
Material 1
Reinforcing Steel Rebar B500B Ø12mm
5 split deliveries · 1 suppliers
Delivery total
180 t
Carbon136,800kgCO₂eq
01-22 08:00 · 40 t cumulative 40/180 t
Stahlbau Ruhr Essen · Foundation cages · Rebar batch 1 — foundation cages
1/5
01-30 08:00 · 38 t cumulative 78/180 t
Stahlbau Ruhr Essen · Core wall cages · Rebar batch 2 — core shear-wall cages
2/5
02-15 08:00 · 35 t cumulative 113/180 t
Stahlbau Ruhr Essen · Tower slab cages · Rebar batch 3 — tower slab cages L2-L6
3/5
03-08 08:00 · 40 t cumulative 153/180 t
Stahlbau Ruhr Essen · Tower slab cages L7-L11 · Rebar batch 4 — tower slab cages mid zone
4/5
04-02 08:00 · 27 t cumulative 180/180 t
Stahlbau Ruhr Essen · Roof slab cages · Rebar batch 5 — roof slab + rooftop plant
5/5
Material 2
Structural Steel S355J2 (Hot-rolled Section)
10 split deliveries · 1 suppliers
Delivery total
380 t
Carbon410,400kgCO₂eq
01-26 08:00 · 35 t cumulative 35/380 t
Stahlbau Ruhr Duisburg · Site lay-down area · Steel batch 1 — temporary works + tower-crane base
1/10
02-08 08:00 · 32 t cumulative 67/380 t
Stahlbau Ruhr Duisburg · Podium frame · Steel batch 2 — podium frame
2/10
02-18 08:00 · 40 t cumulative 107/380 t
Stahlbau Ruhr Duisburg · Tower columns L2-L6 · Steel batch 3 — tower columns lower zone
3/10
02-22 08:00 · 40 t cumulative 147/380 t
Stahlbau Ruhr Duisburg · Site lay-down area · Steel batch 7 — podium secondary frame
4/10
03-02 08:00 · 35 t cumulative 182/380 t
Stahlbau Ruhr Duisburg · Tower columns L7-L10 · Steel batch 4 — tower columns mid zone
5/10
03-10 08:00 · 40 t cumulative 222/380 t
Stahlbau Ruhr Duisburg · Site lay-down area · Steel batch 8 — tower secondary beams + bracing
6/10
03-15 08:00 · 38 t cumulative 260/380 t
Stahlbau Ruhr Duisburg · Tower columns L11-L14 · Steel batch 5 — tower columns upper zone
7/10
04-12 08:00 · 40 t cumulative 300/380 t
Stahlbau Ruhr Duisburg · Rooftop plant · Steel batch 6 — rooftop plant frames + parapets
8/10
04-15 08:00 · 40 t cumulative 340/380 t
Stahlbau Ruhr Duisburg · Site lay-down area · Steel batch 9 — façade brackets + curtain-wall mullions
9/10
05-15 08:00 · 40 t cumulative 380/380 t
Stahlbau Ruhr Duisburg · Rooftop level · Steel batch 10 — rooftop plant frames + parapet
10/10
Material 3
Ready-mix Concrete C30/37 (XC2)
9 split deliveries · 2 suppliers
Delivery total
3,000
Carbon721,500kgCO₂eq
02-02 07:45 · 380 cumulative 380/3,000
BetonWerk Frankfurt Ost · Foundation east · Pour event 1/6 — east foundation raft
1/9
02-04 07:45 · 360 cumulative 740/3,000
BetonWerk Frankfurt Ost · Foundation west · Pour event 2/6 — west foundation raft
2/9
02-12 07:45 · 320 cumulative 1,060/3,000
BetonWerk Frankfurt Ost · Core walls + L1 · Pour event 3/6 — core walls + L1 slab
3/9
02-25 07:45 · 380 cumulative 1,440/3,000
BetonWerk Frankfurt West · Tower slabs L2-L4 · Pour event 4/6 — tower slabs L2-L4 (switched plant for capacity)
4/9
03-12 07:45 · 320 cumulative 1,760/3,000
BetonWerk Frankfurt West · Tower slabs L5-L7 · Pour event 5/6 — tower slabs L5-L7
5/9
03-19 07:45 · 360 cumulative 2,120/3,000
BetonWerk Frankfurt West · Tower slabs L8-L10 · Pour event 7/9 — tower slabs L8-L10
6/9
03-26 07:45 · 340 cumulative 2,460/3,000
BetonWerk Frankfurt West · Tower slabs L11-L12 · Pour event 8/9 — tower slabs L11-L12
7/9
04-01 07:45 · 300 cumulative 2,760/3,000
BetonWerk Frankfurt West · Tower slabs L13-L14 + setbacks · Pour event 9/9 — top floors + setback walls
8/9
04-08 07:45 · 240 cumulative 3,000/3,000
BetonWerk Frankfurt Ost · Tower roof + rooftop plant · Pour event 6/6 — roof slab + rooftop plant deck
9/9
Material 4
XPS Insulation Board 50mm
3 split deliveries · 1 suppliers
Delivery total
3,800
Carbon12,198kgCO₂eq
03-20 09:15 · 1300 cumulative 1,300/3,800
Insulux Brandenburg · Lower-zone façade · XPS insulation batch 1 — lower zone
1/3
04-18 09:15 · 1300 cumulative 2,600/3,800
Insulux Brandenburg · Middle-zone façade · XPS insulation batch 2 — middle zone
2/3
05-08 09:15 · 1200 cumulative 3,800/3,800
Insulux Brandenburg · Upper-zone façade · XPS insulation batch 3 — upper zone
3/3
Material 5
Clay Hollow Brick HLz 1.2/12 (240mm)
2 split deliveries · 1 suppliers
Delivery total
1,200
Carbon34,080kgCO₂eq
03-25 09:30 · 600 cumulative 600/1,200
Ziegelei Rhein Köln · Podium façade east · Brick batch 1 — podium façade east (22 pallets)
1/2
05-05 09:30 · 600 cumulative 1,200/1,200
Ziegelei Rhein Köln · Podium façade west · Brick batch 2 — podium façade west (22 pallets)
2/2
Material 6
Triple-glazed Window (Uw 0.8)
4 split deliveries · 1 suppliers
Delivery total
320 set
Carbon16,768kgCO₂eq
04-05 10:30 · 80 set cumulative 80/320 set
FensterWerk Bayern · L1-L4 façade · Triple-glazed units batch 1 — L1-L4 (80 sets)
1/4
04-25 10:30 · 80 set cumulative 160/320 set
FensterWerk Bayern · L5-L8 façade · Triple-glazed units batch 2 — L5-L8 (80 sets)
2/4
05-12 10:30 · 80 set cumulative 240/320 set
FensterWerk Bayern · L9-L11 façade · Triple-glazed units batch 3 — L9-L11 (80 sets)
3/4
05-22 10:30 · 80 set cumulative 320/320 set
FensterWerk Bayern · L12-L14 façade · Triple-glazed units batch 4 — L12-L14 (80 sets)
4/4
Material 7
Gypsum Plasterboard 12.5mm
4 split deliveries · 1 suppliers
Delivery total
16,000
Carbon29,120kgCO₂eq
05-02 13:30 · 4000 cumulative 4,000/16,000
PlasterPro Sachsen-Anhalt · L1-L4 guest rooms · Plasterboard batch 1 — L1-L4 guest-room partitions
1/4
05-13 13:30 · 4000 cumulative 8,000/16,000
PlasterPro Sachsen-Anhalt · L5-L8 guest rooms · Plasterboard batch 2 — L5-L8 guest-room partitions
2/4
05-18 13:30 · 4000 cumulative 12,000/16,000
PlasterPro Sachsen-Anhalt · L9-L11 guest rooms · Plasterboard batch 3 — L9-L11 guest-room partitions
3/4
05-25 13:30 · 4000 cumulative 16,000/16,000
PlasterPro Sachsen-Anhalt · L12-L14 + corridors · Plasterboard batch 4 — L12-L14 + corridors
4/4
Material 8
Bituminous Roofing Membrane SBS 4mm
2 split deliveries · 1 suppliers
Delivery total
1,800
Carbon8,910kgCO₂eq
05-10 08:00 · 900 cumulative 900/1,800
Dachschutz Bau Wiesbaden · Podium terrace · SBS membrane batch 1 — podium terrace
1/2
05-20 08:00 · 900 cumulative 1,800/1,800
Dachschutz Bau Wiesbaden · Tower rooftop · SBS membrane batch 2 — tower rooftop
2/2
Material 9
Engineered Oak Flooring 22mm (3-ply)
Single delivery
Delivery total
850
Carbon-15,810kgCO₂eq
05-15 13:00 · 850
Parkett Schwarzwald Freiburg · Suite + lobby staging · Engineered oak flooring — suites & lobby
Single
Certifications
BREEAM
4 materials
In review
DGNB
2 materials
Needs data
LEED
0 materials
Needs data